Air Liquide SA has agreed to construct a renewable energy-powered hydrogen manufacturing facility to curb emissions at TotalEnergies SE’s La Mède biorefinery in southeast France.
Anticipated to go onstream 2028, the hydrogen unit will add a capability of 25,000 metric tons a 12 months to the location’s clear hydrogen manufacturing. TotalEnergies earlier partnered with ENGIE SA for the Masshylia challenge, which can produce as much as 10,000 metric tons every year (MMtpa) of inexperienced hydrogen. Although the challenge with ENGIE was launched 2021, it’s anticipated to begin up a 12 months later than the challenge with Air Liquide, in response to TotalEnergies.
“These tasks will cut back the La Mède biorefinery’s CO2 [carbon dioxide] annual emissions by 130,000 tons”, TotalEnergies stated in an internet assertion.
The French vitality big expects low-carbon hydrogen to assist cut back CO2 emissions from its European refineries by about three MMtpa by 2030.
Beneath the brand new EUR 150 million ($157.69 million) partnership, Air Liquide, additionally a French firm, will assemble and function the hydrogen unit. The plant will recycle coproducts from the La Mède refinery. “The hydrogen will then be used within the biorefinery to supply biodiesel and sustainable aviation gas”, TotalEnergies stated.
TotalEnergies has already partnered with Air Liquide for a partly-renewable hydrogen plant to assist decarbonize its under-conversion Granpuits biorefinery in France, its solely different biorefinery in Europe. Air Liquide agreed to speculate over EUR 130 million to construct and function the Granpuits hydrogen unit, which can have a capability of over 20,000 MMtpa. TotalEnergies expects to finish the oil refinery’s conversion by subsequent 12 months.
“Nearly ten years after the announcement of its conversion, La Mède is continuous its transformation and is changing into a low-carbon hydrogen manufacturing middle, thus contributing to the decarbonization ambition of the Provence-Alpes-Côte-D’azur area”, stated Vincent Stoquart, president for refining and chemical substances at TotalEnergies.
In the meantime the Masshylia unit won’t solely contribute to the biorefinery’s decarbonization but in addition serve native prospects on the Fos-Berre industrial-port zone, in response to TotalEnergies.
The Masshylia challenge was to go surfing this 12 months, in response to the companions’ announcement January 13, 2021, which stated the challenge would have a 40-MW electrolyzer. Asserting the challenge with Air Liquide, TotalEnergies stated the Masshylia challenge is now anticipated to begin up its first 20-MW electrolyzer in 2029.
TotalEnergies’s La Mède website was constructed 1935 and transformed 2019 below a EUR 337 million transformation. It may well produce as much as 500,000 MMtpa of renewable diesel utilizing “a huge number of licensed sustainable feedstocks, resembling vegetable oils, used cooking oils and animal fat from the round financial system”, the corporate says on its web site. TotalEnergies is investing an extra EUR 70 million to improve the biorefinery’s amenities to course of as much as one hundred pc used cooking oil and animal fat.
“TotalEnergies is dedicated to decreasing the carbon footprint of manufacturing, changing and supplying vitality to its prospects”, it stated saying its new partnership with Air Liquide. “One of many paths recognized by the Firm is to make use of low-carbon hydrogen to decarbonize its European refineries, a transfer that ought to assist cut back its CO2 emissions by round three million tons a 12 months by 2030”.
Apart from the 2 biorefineries at house, TotalEnergies has six conventional refineries in Europe — three in France and one every in Belgium, Germany and the Netherlands, in response to on-line info from the corporate.
On September 14, 2023, TotalEnergies launched a name for presents for the availability of 500,000 MMtpa of inexperienced hydrogen. “The usage of inexperienced hydrogen ought to keep away from the emission of round 5 million tons of CO2 every year from the Firm’s European refineries by 2030”, it stated then.
On June 7, 2024, it stated it had awarded the primary contract below that tender to Air Merchandise, which can ship 70,000 MMtpa for 15 years.